* Click on package name for more details. All costs are in lakhs. End date cell(col. 5) is highlighted with yellow color where EOT has been issued.
 
Refresh
Sno. Package No. Bond/Package Name * Start Date End Date Agreement Cost Variation Cost Total Agreement Cost Contractor Name Advance Amount Advance Recovered Bond Status Progress Expenditure
1. 1 AF/01B/BC/PIU/PB/UDRP/2018 2018-11-26 2020-06-30 7902.39 0.00 7902.39 M/s NKG Infrastructure Ltd 87.48 87.48 0.34 % 1155.17
2. 2 AF/02/BC/PIU/PB/UDRP/2019 2020-01-01 2021-12-31 6549.44 0.00 6549.44 A.S Enterprise 51.84 18.76 0 % 80.01
Total Cost 14451.83 0 14451.83